The extension and renovation of CHU Saint-Pierre consists of the construction of a new wing as well as the renovation of existing services such as: intensive care unit, operating quarters, medically assisted reproduction, emergencies, laboratories and accommodation units.
- Accommodation
- Intensive care units
- Operation departement
- Assisted reproduction
- Sterilization
- Emergency
- Laboratories
LOCATION
CHU Saint-Pierre, Brussels
SURFACE
25.000m2
CLIENT
Saint Pierre university hospital center
BUDGET
65 Million €
DATE
2009 – 2017
ARCHITECT
BAEV
Study phase
- Budget Control compliance and Review opinions of the granting authorities
- Programming coordination
- Drafting coordination clauses between companies (separate lots)
- Establishment of the overall planning
Work phase
- Project management
- Coordination of 32 separate lots
- Management and work supervision
- Schedule monitoring
- Quantitative approval of progress reports
- Establishment of the provisional quantities carried out by Lot
- Change tracking
- Organization of Provisional Receptions
- Assistance with the negotiation of the accounts